Friday, 19 November 2010

ADMIRAL Sprint 15 Plan

Notes from the planning meeting for sprint 15 can be found at http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_PlanMeeting_15.

The primary goal of this sprint is to complete the work for Phase 1 of the ADMIRAL project.

As such, rather than set a time-frame for the sprint, then pick some activities and tasks to fill it, we have listed the work needed to wrap this phase, the main goal for which is closing the loop from researchers' data, submitted via ADMIRAl to the Library Databank service, and viewed via the web by the original researchers.

This will form a basis for iterative, researcher-led improvements in phase 2 of the project.

Friday, 12 November 2010

ADMIRAL Sprint 14 review

A review of sprint 14 can be see at http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_SprintReview_14.

Progress has been quite satisfying, with several scheduled activities completed, and more progress than planned on the ADMIRAL-to-Databank dataset submission tool,  all in spite of experiencing a disk failure on one of our servers that took about 1.5 days effort to recover. This is balanced by less-than-planned progress on deploying ADMIRAL for the Development Group, and not yet having researcher feedback on the dataset submission interface.

We are still awaiting a finalized Databank API test suite.

A new ADMIRAL instance for the Evolutionary Development has been built and deployed, but has not yet been finally configured and handed over for use by them.

We have a functional dataset submission tool and web interface, but there are some significant usability problems that need to be adddressed before we want to consider showing it to researchers. This remaining work is mainly in the area of dataset selection, and the required server components have been developed and tested: it just remains to update the web page to use the new capabilities.

As intended, we completed work to revise the ADMIRAL local store test suite, before scheduling the sprint reviewed here.

Tuesday, 26 October 2010

ADMIRAL Sprint 14 Plan

Notes from a planning meeting for sprint 14 can be found at http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_PlanMeeting_14.

The planned focus for this sprint is:
  • Deploy ADMIRAL system for Development group
  • Complete repository submission testing
  • Implement a repository submission tool for researchers to use

Monday, 25 October 2010

ADMIRAL Sprint 13 review

A review of sprint 13 can be see at http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_SprintReview_13.

In summary, Progress has been quite satisfying, with most scheduled activities completed, and also some unscheduled progress. Our new recruit is coming up to speed well with the project development and testing activities.

The initial dataset selection and display functions that will allow researchers to view their submitted datasets are functionally complete (apart from finalizing their deployment via the RDF Databank).

We have made substantial progress on updating the local file store system build scripts and test suite, with a view to building a system for use by the Evolutionary Development group.

Some progress has been made on updating and finalizing the Library Services RDF Databank service, but we are still awaiting a version that we can test and use as a target for dataset submission scripts.

For ongoing work, our immediate priorities are to (a) finish updating the local file store test suite, and (b) configure and deploy a system for the Development group. Beyond that, we need to focus on finalizing the RDF Databank API test suite, and building tools to allow researchers to select and submit datasets to the Databank.

ADMIRAL Sprint 13 Plan

Notes from a planning meeting for sprint 13 can be found at http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_PlanMeeting_13.

Due to an unplanned staff departure, sprint 12 was abandoned part way through. Sprint 13 was deferred until a replacement could be engaged. (The intervening period was used to wrap up some development work on the MILARQ project.)

(Further, although the sprint was planned per schedule, writing up the meeting got overlooked until the date of the sprint review, hence this rather overdue post.)

Monday, 6 September 2010

ADMIRAL Sprint 12 plan

Sprint 12 has been planned to run over the next 3 weeks.

The Sprint 12 planning meeting is reported at:
http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_PlanMeeting_12.

The three main activities scheduled are:

  • Deploy ADMIRAL system for Development group
  • Repository submission testing (mainly coordinating with AR)
  • Implement repository content display

Friday, 3 September 2010

ADMIRAL Sprint 11 review

This sprint has been substantially taken up with introducing a new developer to the various ADMIRAL technologies.  Progress (not enough) has been made with improving and debugging the ADMIRAL system generation scripts, but the resulting system is not passing its tests.  Some progress has been made to creating a utility for displaying dataset content in user-friendly fashion.

Review of sprint 11: http://imageweb.zoo.ox.ac.uk/wiki/index.php/ADMIRAL_SprintReview_11